“This puts us on a clear path to securing the full $500 billion, 10-gigawatt commitment we announced in January by the end of 2025, ahead of schedule.”
Said Sep 23, 2025Deadline Dec 31, 2025OpenAI, 'OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites,' September 23, 2025
Across all partners OpenAI blew past 10GW on paper — Altman said on October 28, 2025 that the company had roughly $1.4 trillion and ~30GW of infrastructure commitments. But the Stargate vehicle itself did not close it out: The Information reported in February 2026 that OpenAI fell short of locking in 10GW through SoftBank and Oracle by the end of 2025, with OpenAI citing 'well over 8GW' and $400B+ in play as of early 2026.