“"With PJM's action... we're on track to make history ahead of schedule, helping America achieve energy independence, supercharge economic growth, and win the global AI race" — Three Mile Island Unit 1 / the Crane Clean Energy Center will restart as early as 2027, about a year ahead of the original 2028 target.”
Said Jun 25, 2025Deadline Dec 31, 2027Constellation Energy press release (Business Wire), Crane Clean Energy Center celebration event, June 25, 2025
As of September 2026 Constellation still targets 2027; FERC granted the Eddystone capacity-rights waiver in June 2026, the NRC issued a finding of no significant environmental impact, and a $1 billion DOE loan closed in November 2025.