“Four fabs will be built sequentially at the Yongin Semiconductor Cluster, with construction of the first fab scheduled to begin in March 2025 and be completed in May 2027.”
Said May 2, 2024Deadline May 31, 2027SK hynix AI-era vision press conference / press release, Icheon, May 2, 2024
On track so far: SK hynix broke ground on the first Yongin fab in late February 2025, slightly ahead of the March plan, with the 9.4 trillion won facility still targeted for completion in May 2027.