One prediction, on the record

Energy & Data CentersPartially correct
“We continue to see strong data center growth in Virginia and have already connected 14 new data centers year-to-date. We now expect to connect 16 data centers in 2024, up from 15 as of our last update.”

Virginia electric utility; Q3 2024 earnings call prepared remarks

Said Nov 1, 2024Deadline Dec 31, 2024Dominion Energy Q3 2024 earnings call, November 1, 2024

Dominion ended up connecting 15 new data centers in 2024 with a combined capacity of nearly 1 GW — one short of the raised 16-connection forecast — per its Q4 2024 earnings slides and FY2024 annual report.